SOUTH PORTLAND — Finding $4 million to trim from the
long-awaited South Portland High School renovation project is proving harder
than some had hoped, causing tension to mount on the building committee tasked
with finding those savings.
The building committee was expected
to make cuts at meetings this week, but those meetings have now been postponed
while the project engineer, Portland-based Harriman Associates, continues to
negotiate with the low bidder, PC Construction.
The committee is now scheduled to
vote on cuts Tuesday, March 27, and Thursday, March 29. Both sessions will
begin at 5:30 p.m. in the high school library. In the meantime, some committee
members appear vexed that decisions seem to have been made without their input.
“I
feel like there’s stuff going on obviously behind the scenes,” said Carrie
Hull-Indorf at a March 15 meeting. “We’re not involved in any of the
discussions. We have no information on any of it. Frankly, if we can’t discuss
things, why do we even bother to have a committee?”
“My
understanding was that everything was on the table,” said school board member
Jeff Selser, at a March 8 session, “but things have come off the table without
the participation of this committee.”
Selser appeared frustrated that
Superintendent Suzanne Godin and Harriman architect Dan Cecil told city
councilors energy-savings certification was “off the table” as a possible
project cut, as is Selser’s proposal to rebuild Beal Gym rather than try to fix
the structurally ailing section of the high school.
The high school renovation was
budgeted at $47.3 million, including a $41.5 million bond OK’d by voters in
November. Administration, engineering and other costs left $39.26 million for
construction, but PC's bid, the lowest of four opened Feb. 23, was $43.24
million. That's left school officials scrambling ever since to bridge the gap.
According to Cecil, his firm has
worked with PC to hammer out a list of "more than 200" cost-savings
ideas. However, Robbins told building committee members Thursday evening that
marathon talks have yet to narrow in on dollar amounts for many proposals,
leaving nothing concrete to vote on.
"The information, is just not there,"
committee Chairman Ralph Baxter Jr. told the group. "I understand,
I'm frustrated, too, but they're working doing their thing and we've just got
to be patient."
“I think everyone is feeling the
frustration of having to wait right now,” said committee publicist Justine
Carlisle. “We all want all the information. We want it today and we don’t want
to wait.”
Following cuts, a final budget will
go to the school board April 2 and the City Council April 4.
Baxter said the building committee
may also meet the weekend of April 1, if necessary, in order to make the agenda
for the school board and council meetings. As long as those votes happen on
time, he said, construction on the 33-month project can still being as planned
in mid April.
No comments:
Post a Comment